Caine Hill Shaft - One of Britains Deepest Caves?
By Tony Jarratt
To some,
digging is a fairly tedious chore, and they are only sustained by the hope of
triumphs to come. To others the digging operation itself is fascinating. It is
seldom simple.
Digging for
Mendip Caves W. I. Stanton Studies in Speleology, Vol IV, 1983
Continued from BB 528. Photos by Sean Howe.
Further Digging 20/5/07 27/10/07
Errata: The photo
of Dudley Herbert on page 21 of BB 528 is actually of Mike Thompson.
Robin Main of
Priddy has confirmed that Caine Hill is the name of the steeply sloping field
behind Manor Farm but has no idea of its derivation. A character met in the
Queen Victoria Inn claims to have dug the foundations for the adjacent house
and stated that the open hole found was not as big as we were led to believe.
On the 20th May
Trevor Hughes, Jane Clarke and the writer, assisted on the surface by Tim
Andrews, Darryl Instrell and Bob Smith removed 64 loads of spoil and loaded
Tims truck with over 1½ tons for disposal. Tim also donated another section of
alloy ladder, which your scribe used next day to replace that on the entrance
shaft fixed to a shorter section. This was done as he had deepened this shaft
and cleared clay from the ledges below to make a better bag stacking area. He
hauled out 16 loads from here and then continued digging in Root 66. Tim later
went to the end for a look and was suitably impressed. He was delighted that he
now owns an actual cave as well as a mineshaft! 27 more loads came out on the
23rd when Jake Baynes, Paul Brock and the writer attended. The second pitch was
re-rigged with an alloy builders ladder to ease bag hauling and digging was
continued at Root 66. More work was done here, by your scribe on the 25th but
the poor quality of the air drove him out after an hour. Conditions had
improved on the following evening, possibly due to a change in atmospheric
pressure, when he carried on with this project. On the 27th, despite atrocious
weather, 55 loads were hauled out by Bob, Jane and the writer all from Root
66 and next day Jane, Bob and Hannah Bell stacked lots of clay on a
convenient ledge ready for bagging and hauled 1 token load out. This clay was
bagged on the 30th when digging continued at the end and 35 loads reached
daylight; Henry Dawson, Bob and the writer making up the team. Several more
small airspaces were revealed. Further digging and bag-filling was done here by
your scribe on the 1st June and on the following day he concentrated on the dig
in the main rift below Boxwork Passage where a tiny airspace was revealed on
the NE side. A return was made next day when he cleared the remaining clay and
a large rock step from the entrance shaft. 18 loads were hauled out. Another
solo trip on the 4th June resulted in re-positioned entrance ladders, a
scaffold bar and pulley on the second pitch, more digging below Boxwork Passage
and 20 loads out warm work in the prevailing fine weather. 50 more came out
on the 6th when Hannah, Helen Stalker, Pete Hellier and your scribe cleared the
cave temporarily!
Jake and the
writer were back at the Boxwork dig on the 8th June when 19 bags were filled
and hauled out and an arm-sized phreatic tube opened up on the SW side of the
main rift. Next day the latter dug and filled bags at both sites. He returned
on the 10th with Bob, Trev and Hannah to haul out 50 loads, some of these being
freshly dug from both sites where the diggers both got surprisingly cold. 1
token load came out on the 11th June when the writer concentrated on the
Boxwork dig. A palm-sized slab of galena (lead sulphide PbS) 1-2 cms thick and
weighing 800 grammes (1½ lbs) was disinterred from the clay floor indicating
that the Old Men could well have been prospecting for this as well as ochre.
Derived from a primary hydrothermal
vein deposit located many metres above the present land surface or from
limestone dissolution around a minor stringer of ore, this residual,
secondary galena has been smoothed and rounded during its downward progression
from its original position indicating the extreme age of the in-filled cave
passage in which it was found (Barrington and Stanton, 1977, Stanton, 1991). A
whitish coating may be cerrussite (lead carbonate PbCO3). Thick veins of
sandstone-like rock in the walls of the rift here may be red-brown, silty
mudstone, Triassic neptunian dykes formed from either seafloor or desert
deposits which were washed or blown into open joints and fissures in the
underlying bed rock and often associated on Mendip with primary mineralisation.
Another airspace was revealed on the NE side with a void visible a couple of
metres away but inaccessible without banging or chiselling. The airspace opened
on the 2nd June connects with this so further removal of the clay floor was
planned in the hope of entering it from below. Lots of bags were filled and
stacked and even more added to the pile on the 12th ready for the Wednesday
night team on the morrow. This turned out to be limited to Bob, Hannah and the
writer but being of tough stuff they managed to load Tims truck two thirds
full and haul out another 50 loads. 14 more came out on the 15th when Bob and
your scribe continued digging in the floor. Further digging was done by the
writer next day and on the 17th a strong team comprising Bob, Fiona Crozier,
Trev, Duncan Butler and your scribe worked at both sites until poor air
conditions drove them out after 55 loads had been removed. Bob came up with a
name for the second drop Son of a Pitch! A solo digging session by the writer
next day was soon halted by the atrocious lack of oxygen but several bags were
filled at the base of Son of a Pitch and 2 reached the surface. A walk around
the field to the north on a quest for other mine workings revealed little of
interest.
New digger (and
New Inn barman) Keith Creagh joined Jake and the writer on the 20th when the
air was improved by the use of the vacuum cleaner to allow further digging in
the pitch floor and the removal of 23 loads. Two days later the vacuum cleaner
pipe was replaced with a longer length of greater diameter giving plenty of
spare at Root 66. Here Fiona filled nine bags and used a valve and 1.5 litre
bottle of compressed air to avoid the unpleasantly claustrophobic effects of
the poor air conditions. The bag supply was kindly donated by interested
villager Mark Glover. Meanwhile the writer filled lots more bags at the base of
the ever-descending Son of a Pitch having no bad air problems. The duo
returned to their respective digs on the 24th in relatively excellent air
conditions. Thanks to the timely arrival on the surface of Steve Woolven and
Gary Cullen the total hauled out today was 47 loads. The atmosphere was much
poorer next day when your scribe dug at both sites and removed 4 loads but when
he returned with Fiona on the 26th conditions had dramatically improved and both
sites were dug further. 1 load came out the rock on which the first section
of the entrance ladder was perched and erroneously thought to have been holding
up the ginging! On the 27th the air was again poor but Hannah, Bob, Jake, Keith
and your scribe dug a little at Son of a Pitch and removed 50 loads. Tim helped
load up his truck with a ton or so of clay and the team accompanied him to the,
as yet unseen, spoil dump where they were relieved to find that there is ample
space for another 1,000+ tons. Unfortunately, in the fullness of time it will
all get washed down Swildons!
Solo digging
becoming popular, Fiona did a stint at Root 66 on the 28th June and stacked
about ten bags. She filled another six
on the following evening while the writer dug and drilled at Son of a
Pitch. A small, fragile lump of mineral
weighing 340 grammes (12 ounces) was recovered from the clay floor. This was
identified by Nick Richards as goethite (brown hematite Fe3+O), an iron oxide
associated with limonite (yellow ochre) and derived from the degradation of
iron pyrites. Like the galena this is a residual deposit that has worked its
way downwards from the primary veins way above. He also explained that the,
sometimes powdery surface of the cave walls indicates that some of the
limestone has been transformed to dolomite. More digging was done here by the
writer on the 30th June and next day he returned with Fiona, Duncan, Trev, Bob,
Helen Brook (S.W.C.C. now also B.E.C.), Jinni King (Cardiff U.C.C.) and Kate
Humphries (C.U.C.C.) to haul out 56 loads and continue digging at both sites. A
passable route was dug to connect the bottom of Son of a Pitch with the
continuation of the main rift and a small cord charge was fired in an attempt
to gain access to the void in the NE wall near the base of the pitch. On a solo
trip next day the writer was delighted to find that the bang had done a
surprisingly good job and produced a vast amount of broken rock. Another bang
was required to reach the void but air conditions did not encourage a lengthy
stay today. Wednesday 4th July saw 7 bags out, mainly filled with bang debris.
Hannah and Bob both put up with unpleasant fumes lingering at the top of Son of
a Pitch while below, in more pleasant conditions, your scribe laid another charge.
This was ready just as Sean Howe arrived for a very short trip before the
bang was fired.
The writer
returned on the 6th intending to fire up the vacuum but Tim was at Priddy Folk
Fayre so he nipped down to check the air and was amazed to find it good. More
bang spoil was removed and another two shot-hole charge fired. The novelty
tonight was the sound of live folk music heard from the dig face! Assisted by
Bob your scribe cleared the spoil on the following evening and placed yet
another two shot-hole charge. After firing, the duo savoured the delights of
the appropriately named Potholer bitter at a very conveniently located marquee.
The air was then left to clear for a few days and on the 11th July the writer
filled and stacked bags at the banged bedding where it was now possible to
crawl in and look down a small rift to the north. Suffering from a cold and
with the air tasting unpleasantly metallic he clambered out to meet latecomers
John Noble and Paul. The former went for a brief look around while the latter
hurled obscenities from above. Not a particularly productive Wednesday evening!
The next visit
was on the 14th when your scribe drilled one shot-hole at Son of a Pitch and
filled bags at Root 66. Next day he and Trev continued work here and on the
16th he was back with John. More bags were filled and stacked and another two
shot-holes drilled but the air was atrocious so they persevered and hauled 24
loads to surface before retiring leaving the vacuum cleaner running to
refresh the place. This worked well and on the 18th July Fiona and your scribe
enjoyed the conditions while filling bags at both sites. A charge was fired at
Son of a Pitch and a token 2 loads reached the surface. A brief visit was made
by the writer on the 21st when the air was found to be good enough to clear
some of the bang-debris and next day Trev continued with this while Fiona dug
at Root 66 and Duncan enlarged the connecting rift between the two sites. Your
scribe acted as bag hauler for the three diggers. The worsening air quality and
bang fumes released from the mud eventually stopped play but not before 50
loads went out. Another 30 reached the surface next day when John finally
cleared the blasted rock and the writer dug at the other two sites. This was only
possible because of the use of the vacuum cleaner and it was actually far more
pleasant underground than on the monsoon-drenched surface. Another 23 loads
came out on the 25th when all three sites were dug by your scribe and Henry D.
arrived in time to struggle with the full bags after pioneering the use of the
vacuum hose as a speaking tube! 1 load a phreatically sculpted rock flake
came out on the 28th when the writer filled bags at Root 66, partly with vivid
orange ochre. 34 loads came out next day when Paul and Fiona dug at Root 66,
Jane and your scribe continued clearing the connecting rift and Nicks Harding
and Richards hauled from the surface with the latter briefly studying the
geology of the cave in preparation for another visit on a less hectic occasion.
Bob assisted on the surface due to alcohol-induced cracked ribs the second
team member whose underground exploits were curtailed by over zealous cycling!
Root 66 was dug
again on the 30th July by enthusiastic new digger, Sissel Balomatis (Cheddar
C.C.) and the writer. 21 loads were hauled out and a two shot-hole charge was
fired in the dig just above the floor of Son of a Pitch. Much of the
bang-debris was cleared by Siss and Paul on the 1st August when they also
assisted Jake, John and your scribe to load over three tons of spoil into Tims
truck which he took away to the dump. On the 3rd the writer filled thirteen
bags at Root 66. He was back on the 5th with Fiona when much digging took place
here and 18 loads came out. A solo visit next day saw more digging and rock
removal at the same site. Mike Willett joined the team on the 8th and dug at
Root 66 while Helen S. and your scribe shifted bags, 48 coming out in total. A
power cut stopped the vacuum cleaner for a while and later, in the Hunters the
culprit was revealed as a local who had chain-sawed a tree branch which,
dropping on to the cable severed the village electric supply. He wishes to
remain anonymous so we will call him J.C.B.
On the 9th Tony
Audsley commenced work on pointing the entrance ginging in preparation for the
replacement of the rusting Acro-prop with a permanent lintel. He noted possible
traces of original lime mortar. Some token digging was done by your scribe in
Root 66 on the 11th and next day he returned with Duncan and Ray Deasy (on his
annual visit from Australia) to continue with this until stopped by an apparent
rock pillar in the middle of the passage. Duncan concentrated on enlarging the
bottom of the main rift. On the 13th Tony continued fettling the entrance shaft
while the writer laid a five shot-hole charge in Root 66. After firing this the
duo retired for lunch then returned to continue with their projects. The
mornings bang had done a good job so a two shot-hole charge was fired to
enlarge the squeeze from the main rift into Root 66. A total of 6 bags of spoil
came out today. The spoil from the banged squeeze was cleared on the 15th by Mike, Helen, Jeff Price and the writer
when a total of 34 bags and skips reached the surface. The bang had brought
down a vast amount of rock - far more than it should have - indicating that the
roof here was potentially unstable and
that blowing it down had been a wise move! Two days later
the writer bagged up much of the spoil from the bang at the end and this was
hauled halfway out on the 20th, when he was joined by Jeff. 12 loads came out
today, mainly rock and clay cleared from the banged squeeze. Tony measured up
the entrance shaft. On the 22nd August the banged squeeze was finally cleared
by your scribe when a possible way on behind clay infill was revealed to close
down. Mike continued digging at the end of Root 66 and Bob took CO2 samples
with an expensive electronic gadget. He recorded percentages of 0.5 at the
bottom of the entrance shaft, 1.3 1.6
near the banged squeeze and 2.34 at the Root 66 dig. A flame safety lamp used
in conjunction dimmed as he descended the cave and expired at the banged
squeeze. He was only able to re-light it on the surface. 16 loads were hauled
out and many more left for future removal.
2 loads of spoil
from Tonys ginging repair project came out on the 27th August when he prepared
the entrance shaft for the casting of the concrete lintel. Meanwhile the writer
cleared the terminal Root 66 dig and laid a four shot-hole charge.
Unfortunately this misfired so was left for a day as a precaution. Being a bank
holiday there was a plentiful surface support team of Rich Witcombe, Paul
Weston and the two Nicks. The charge was rewired on the 28th but again failed
to fire as it did twice more next day when all connections were changed and
the firing cable tested. Even Tims lawnmower battery was tried in vain and
your scribe, baffled, gave up the attempt preferring to return on the 30th with
a fresh detonator and length of cord to join the two sets of double shot-holes.
This thankfully did the business and on the 2nd September Trev and the writer
bagged up lots of spoil and moved full bags towards the entrance. 1 load came
out. Tony continued with his entrance fettling next day and drilled the solid
walls while your scribe got rid of much of the blasted rock dumped on the
surface by adding it to the drystone wall across the road and bringing it up
towards its original height. Root 66 saw action again on the 5th when Mike and
the writer filled bags at the end and, aided by Jeff, hauled 35 out. A
clay-filled and easily diggable phreatic tube was opened up beyond the banged
section and hope was restored. On the 8th September the writer filled and
stacked lots of bags here until the air went stale. Digging did not reveal the
ceiling of the tube thus ensuring that it was pleasantly spacious. Free
diving was almost necessary to regain the surface through the hordes of
mosquitoes now infesting the main rift! Next day he returned with John to
continue digging and hauling. 53 loads came out. Bob and Jane briefly assisted
on the surface. The two returned next morning and pushed on into the phreatic
passage now almost of kneeling height. John poked upwards with a crowbar to
reveal a phreatic ceiling and your scribe then went in for a look. A lip of
ochreous clay was pulled down to reveal a lengthy and (allegedly) draughting
airspace. Jane arrived to fill more bags and confirm the draught. Tony,
assisted by Paul, continued with lintel preparations and Rich professionally
repaired more of Robin Mains drystone wall opposite Tims house an excellent
PR job. They continued with these projects in the afternoon whilst the writer
filled more bags at the end and decided that the dig now looked more promising
than ever before and almost certain to yield significant cave.
Tony spent six
hours working in the entrance shaft on the 11th September, assisted from the
surface by Alice Audsley. He constructed a timber former, intending to install
this at a future date. On the 12th Mike and your scribe continued with the
magnificently easy dig at the end and, assisted by Jeff, Pete, and Tim Ball on
the surface, hauled out a total of 60 loads. Mike was perplexed by the
disembodied voice of Tim issuing from the vacuum pipe, as it appeared to
emanate from a blank rock wall! More bag-filling was done by the writer next
day and on the 14th Tony continued
fettling the shaft while Tim Andrews went almost to the end to check on
progress. The following day Mike moved all the full bags to Son of a Pitch and
filled another eleven before poor air stopped play. In the evening the writer,
Henry D. and Barry Lawton filled a few more bags at the working face and then
hauled out 74 loads, clearing the cave. Life was much improved by the use of an
electric leaf blower provided by Tim A. to blast fresh air down the vacuum
hose. The 16th saw your scribe, Duncan, Barry and Bob removing 26 loads all
freshly dug from the end. Two shot-holes were drilled in the side passage just above
the floor of Son of a Pitch. Two more were drilled next day when the writer and
Henry Bennett dug at the end and brought out 4 loads. Tony laboured in the
entrance shaft and on the surface to complete the lintel framework and could be
heard, as if above, from the end of Root 66. Mike, Jane and your scribe were
back at the working face on the 19th to dig and haul bags and the following
evening the latter banged the four outstanding shot-holes, Judy Andrews
actually firing the charge. He returned to clear these on the 24th but was not
encouraged by the tiny way on so continued digging at the end. The almost 2m
high passage here transpired to be a choked roof joint with the main phreatic
tube continuing at the same level below good news. He was joined on the
surface by Tony whose open-topped Land Rover was commissioned to deliver a
rigid steel ladder from the Belfry.
On the morning of 26th September Tony washed down the
entrance shaft walls, getting soaked in the process and later Mike and the
writer hauled 22 loads out, moved full bags towards the entrance and filled
many more at Root 66. Phil Coles arrived providentially at knocking off time
and was impressed with the progress made since his last visit. Three shot-holes
were drilled in the walls of the main rift as the commencement of a project to
create a skipway between Root 66 and Son of a Pitch. Study of the geological
map indicated that the cave is south of the Priddy Fault and running parallel
in the direction of Cowsh Aven Series in Swildons Hole to the east. The
estimated depth puts the current end of the cave almost at the level of
Swildons / Priddy Green Sink entrances - indicating that a connection with
this system is more likely than the hoped for breakthrough into ancient fossil
passages heading towards Cheddar. Rich has suggested that the phreatic
Tubledown dig on the western side of the Swildons Five streamway may be a
possible contender. A link would add 15 metres to Swildons current depth
resulting in a system 169 m (554.49 ft) deep and a connection to Wookey Hole would make the total depth, at the
present state of exploration, some 279 m (915.39 ft) one of the deepest in Britain; the Wigmore
Swallet Goughs Cave potential being 296.4 m (972.4 ft) . Time and hard work
will tell but its nice to know that B.E.C. explorers are heavily involved with
both! Ogof Ffynnon Ddu, incidentally, is at least 308 m (1010.55 ft) and will
probably forever be Number One. At least one cave in northern England has
similar potential to the Mendip systems but the writer has no information on
this to hand.
More digging took
place at the end on the 30th when Trev and your scribe also moved full bags
towards the surface. Tony and Pierre Abastado (Marseilles via Estonia) then
arrived and the rest of the afternoon was devoted to transporting all the full
bags on the surface to the spoil dump, utilising both available Land Rovers
an estimated six tons! On the following day your scribe filled more bags at the
end and drilled three more shot-holes in the main rift, which were later
charged with cord and fired by Pierre (as a recompense for Waterloo). Tony,
assisted by Pierre and Alice and Rosie Audsley laboured to install the lintel
shuttering in the entrance shaft. Further work was aborted due to a duff cement
mixer. Weather conditions were atrocious but 10 loads came out today. The
writer also surveyed the cave resulting in a current length of 22.90 metres and
depth of 12.41 metres. Tony and his team returned next day in better conditions
and with a working cement mixer and successfully constructed the lintel with a
bag of cement and five bags of ½ to dust. He was back on the 5th to reduce the
shuttering. On the 7th October 33 loads came out courtesy of Trev, Carole White
and the writer. One detonator from the last bang had misfired but the problem
was resolved by Trev. Lots of B.E.C. dinner survivors visited but failed to
dirty their hands! Your scribe and Carole were back next day to take a Land
Rover load of bags to the dump, clear the latest bang spoil and drag bags
around the cave until driven out by residual fumes. More lintel work was done
by Tony next day - a magnificent construction bearing the inscription BEC 2007,
above which is a Scandinavian runic carving doubtless intended to curry favour
with the gods of the cave (or it could be a sort of masons mark!). A drag tray
was installed in the widened main rift on the 10th and Carole, Mike, Jake, Phil
and the writer hauled 60 loads to surface, most of which were dumped by Land
Rover on the following evening. On the 12th your scribe returned to widen the
skip-way, shift bags and dig at the end but was a little dismayed to find the
terminal passage trending to the right (south east) and indicating that the way
on may be in the floor. On the 14th, accompanied by Trev, he moved bags
throughout the cave.43 loads reached the surface. 2 more came out on the 15th
when the writer filled lots more at the end and took a Land Rover load to the
dump. The 17th October saw Mike, Siss, Paul, Sean, Pete and your scribe moving
bags throughout the cave and Phil and Jake hauling 90 loads to the surface in a
magnificent team effort. Some digging was done at the end. Jane and your scribe
filled more bags here on the19th and reached a smooth limestone floor. All full
bags on the surface were dumped. The writer returned next day to fill many bags
and reveal much more of the floor. When finally cleared this will give the
passage a superb cross section.
On the 21st
October Trev (as a birthday treat) and the writer hauled bags throughout the
cave and attempted to break up a large rock obstructing the south-easterly way
on but decided that bang was needed. This was done by your scribe next day
after lots more bags had been filled. More bag-hauling was done on the 24th by
Mike and the writer. 22 loads came out and the bang debris was cleared to
reveal the passage seeming to turn to the left beyond the site of the late rock
and following the general trend east-north-east. The latter filled more bags
here next day and on the 26th and 27th he was back continuing this work. Vast
amounts of ochreous clay need to come out but plenty of small airspaces are
encouraging and there is no shortage of room in this stunningly pleasant and
easy dig.
Thanks are due to Henry Bennett and Madphil Rowsell for
computing the survey figures.
References:
BARRINGTON, N.
and STANTON, W. I. 1977. Mendip, the Complete Caves and a View of the
Hills. Pp. 228-229.
STANTON, W.
I. 1991. The habitat and origin of lead ore in Grebe
Swallet Mine, Charterhouse-on-Mendip, Somerset Proc. Univ. Bristol Spelaeol. Soc., 19
(1), pp 43-65.
To be continued in BB 530.